Work on phase two of Inverness West Link progressing well

west link phase 2
Aerial photo of the site from the North – dams installed and piling rig working on West abutment

Contractors working on the second stage of the Inverness West Link bypass have said they are making good progress.

Road surfacing started on November 5, with access to the canal and roundabout prioritised to allow it to open for the Regatta on 9 and 10 November.

Tow path diversions and temporary car parking for the rowing club were also installed.

The sheet piling to the new wharf began on 10 November using an 80-tonne piling rig with vibrating hammer.

The canal was closed on 18 November to allow the installation of coffer dams at the extents of the bridge and wharf. Pipelines and pumps were also installed for the over-pumping operation.

Constructors are required to keep the canal downstream topped up, which requires 750 litres a second being pumped between the upstream and downstream dams. 

The planned works for the next month include:

  Piling of East and West abutments

  Dewatering of the canal

  Concrete tie wall and anchors

  Deep drainage across A82

  Duct installation across the canal

The West Link project has significantly enhanced accessibility since the completion of Phase 1 back in December 2017 and Highland Council is looking forward to all the benefits that Stage 2 will bring for local residents, businesses and visitors to the City of Inverness.

west link

Driving sheet piles on wharf

kerbs

Kerbs & Surfacing on the canal access

bus

Surfacing and new bus stop on new General Booth Road

rock dam

Installing Rock Dam across the canal with wheeled shovel – Silt Curtain in place

 

17 Dec 2019