Nairn Academy Update

Pupils in secondary 4, 5 and 6 will return to Nairn Academy tomorrow (Wednesday) as the clean up continues after dust and debris were found in the upper floor of the school following weekend roof works.

Secondary 3 pupils will return on Thursday and Secondary 2 pupils on Friday.

Due to the extent and nature of the debris, it is likely that the maths and computing rooms will remain out of commission for the next three or four weeks.

Arrangements for schooling next week will be confirmed later in the week.

The school was closed to all pupils at noon on Monday after debris was found in the maths and computing classrooms and upper floor concourse.

Contractors had been working at the weekend on preparing the roof for the installation of 24 solar panels. The vibration of the works resulted in damage to the ceiling and the release of dust and debris.

Air and dust sampling in the affected area has identified no evidence of asbestos within the air space but asbestos has been found in flakes of artex debris on the floor. The presence of asbestos in artex is known but presents a low risk to health.

Discussions are ongoing within the school to determine a clean-up programme which minimises disruption to the working of the school.

The Council has advised the Health and Safety Executive of the incident and of its plans to deal with the contamination.  

3 Mar 2009